Call Us Today! 1-800-895-3254
[email protected]
Microsoft Training
Integent offers a comprehensive portfolio of training services, with an ideal fit for every organization. Ranging from general courses to custom solutions, we have you covered.
Learn About TrainingSee Full list of Courses
Microsoft Consulting
Integent provides consulting services for a variety of Microsoft applications including Microsoft Project, Project Online, Project for the Web, Dynamics 365, and Microsoft SharePoint.
Learn About Consulting
Microsoft Support
Microsoft technologies set the standard for project portfolio management, business applications, collaboration, and more. Integent has flexible solutions to support every customer.
Learn About Support
Microsoft Project
Integent has the knowledge and experience to help design and deploy a solution to help your organization manage projects and resources more effectively
Learn More About Microsoft Project
Microsoft Dynamics 365
Integent can help you nsure business continuity with a custom cloud solution that connects sales, service, finance, and operations teams to deliver results.
Learn More About Dynamics 365
Microsoft SharePoint
SharePoint is Microsoft’s collaboration platform that is a place where team members can communicate, exchange data, share files and much more.
Learn More About Microsoft SharePoint
Microsoft Power Platform
Consisting of Power BI, Power Apps, Power Automate and Power Virtual Agents, the Microsoft Power Platform helps streamline and improve business functions.
Learn More About The Power Platform
About Integent
Integent was founded in 2009 on the principles of building long-lasting relationships with customers, exceeding expectations, and providing outstanding customer service. 

We’re dedicated to providing a customized solution backed by our knowledgeable team of Microsoft experts.
Discover What Makes Us Different
GSA Schedule
Integent is GSA Schedule Contract holder. A GSA schedule helps simplify selling our services to government customers.
Read More Here
News
Stay informed on Integent’s latest company updates and other important industry information. Our passion is customer success.
Read The Latest News
Videos
Learning new software doesn’t have to be difficult with our library of dozens of free training videos. Our video training always has something new.
Browse Our Training Video Library
Blog
Our industry experts share best practices and common pitfalls to avoid, in order to get the most out of your technology solutions.
Discover More

November 21, 2021

How To Add A Milestone Using Microsoft Project

What is a Milestone?

Project Milestones are tools used in project management to mark specific points along a project timeline in a Gantt chart view in a project schedule. A project management tool such as Microsoft Project will generate views and reports of milestones that help team members and even resource managers understand important events and/or goals. A milestone looks different in a Gantt Chart than regular project tasks in that they are represented by a black diamond. Whether a simple or complex project, milestones are a very important aspect of project management.

These points may signal anchors such as a project start and end date, or a need for external review or input and budget checks. In many instances, milestones do not impact project duration.

Microsoft Project and Portfolio Management (PPM)

When using Microsoft Project Professional in conjunction with Microsoft Project Online, organizations have the ability to perform project portfolio management (PPM). Project management software of this type allows selection of portfolios that align with business objectives. The product also provides robust collaboration capabilities as well as advanced reports and dashboards with Power BI is added to the mix.

Adding a Milestone, Step-by-Step

Before your project gets started, it is a very good idea to mark its major events/goals with milestones. 

Add a Milestone with a Duration of Zero in Office 365 Microsoft Project

A quick way to use Microsoft Project to Add a Milestone it so add a task to your project plan and set the duration to zero.

1. Navigate to View, then in the Task Views Group, click Gantt Chart.

Task Views Group in MS Project

2. Enter the name of your new milestone in the empty cell just created.  This will be the task you turn into a milestone.

In my case I insert a row above row 6, and type the milestone name in the empty cell as: Self-Assessment Complete.

3. In the Duration field, enter a 0, then press the Enter key.

The milestone symbol is now present in your Gantt Chart, reflecting the milestone you just created.

milestones with 0 duration in microsoft project - full screen

Add a Milestone with a Duration

Sometimes a milestone takes time. For example, the approval process at the end of a stage or a phase could take days or even a week. In this case the milestone actually takes place over a period of time.

1. From within Microsoft Project, Navigate to View, then in the Task Views group, click Gantt Chart.

Task Views Group in MS Project

2. Insert a new task and enter a name, or pick a new, existing task that you want to turn into a milestone.

In my case I insert a row above row 12, and type the milestone name in the empty cell as: Opportunity Definition Complete.

3. From the Task ribbon, in the Properties group, click View Task Information.

Task Information from MS Project

4. Find and click on the Advanced tab. On the Advanced tab, enter a duration for your milestone in the Duration box.

5. Still on the Advanced tab, locate the Mark task as milestone checkbox, and select it.  When finished, click the OK button.

Task information advanced tab where you mark as milestone in ms project

On the Gantt Chart, the milestone symbol appears on the last day of the task. It doesn’t appear as a bar, even though it has duration.

View of duration-based milestone in gantt chart ms project

Adding an External Milestone Scenario

Sometimes a milestone may be affected by a task in an external project.  

As we have in previous examples let's create a milestone in our external project to show when the activities have been completed.

Create Milestone in External Project using Microsoft Project

1. Type the name of the milestone in the first empty cell.

In our example we enter "Evaluation Complete" in row 6.

2. Type 0 in the Duration Column. Also, make sure the milestone has a Task Predecessor.

In our case we link row 5 and row 6 using a Finish to Start relationship.

view of milestone in gantt chart and table in microsoft project

Returning to our main project, we already have a task which incorporates all the activities of the Evaluation set of activities: Review and modify the strategic plan. We are going to link the milestone from our external project to this task.

Open Both Projects in Blank Master Project

The next steps require us to insert our two projects into a new, blank project. We are therefore using the blank project as a temporary master project to create the external dependences. To learn more about master projects you can watch the video How to use master projects and subprojects in Microsoft Project Online.

  1. Save and close both projects
  2. Open a new, blank project
  3. Navigate to the Project ribbon, then in the Insert Group select Subproject.
  4. Here we select our external project.
  5. Select the Subproject button again
  6. Now we select our main project.
  7. Expand both projects.
View of Milestone with duration in ms project Gantt Chart view

Create External Dependency to Milestone

  1. Select the milestone from the external project, hold down the control key then select the dependent task (Review and modify strategic plan) in the main project.
  2. In the Schedule group of the Task ribbon, select the Link the Selected Tasks button

We are also going to link the beginning of the tasks such that the external activities will start at the same time the dependent tasks in the main project start.

  1. Select the predecessor task in the main project.

In our case we select the Summarize Business Approach task in the Evaluate Business Approach group of tasks.

  1. Select the first task in the external project

in our case we select Determine financial requirements

  1. In the Schedule group of the Task ribbon, select the Link the Selected Tasks button
external tasks all linked between project schedules with ms project

There you go folks. Remember, the process is the same with Project 2016, Project 2013, Project 2010 and other versions of Microsoft Project.