Call Us Today! 1-800-895-3254
[email protected]
Microsoft Training
Integent offers a comprehensive portfolio of training services, with an ideal fit for every organization. Ranging from general courses to custom solutions, we have you covered.
Learn About TrainingSee Full list of Courses
Microsoft Consulting
Integent provides consulting services for a variety of Microsoft applications including Microsoft Project, Project Online, Project for the Web, Dynamics 365, and Microsoft SharePoint.
Learn About Consulting
Microsoft Support
Microsoft technologies set the standard for project portfolio management, business applications, collaboration, and more. Integent has flexible solutions to support every customer.
Learn About Support
Microsoft Project
Integent has the knowledge and experience to help design and deploy a solution to help your organization manage projects and resources more effectively
Learn More About Microsoft Project
Microsoft Dynamics 365
Integent can help you nsure business continuity with a custom cloud solution that connects sales, service, finance, and operations teams to deliver results.
Learn More About Dynamics 365
Microsoft SharePoint
SharePoint is Microsoft’s collaboration platform that is a place where team members can communicate, exchange data, share files and much more.
Learn More About Microsoft SharePoint
Microsoft Power Platform
Consisting of Power BI, Power Apps, Power Automate and Power Virtual Agents, the Microsoft Power Platform helps streamline and improve business functions.
Learn More About The Power Platform
About Integent
Integent was founded in 2009 on the principles of building long-lasting relationships with customers, exceeding expectations, and providing outstanding customer service. 

We’re dedicated to providing a customized solution backed by our knowledgeable team of Microsoft experts.
Discover What Makes Us Different
GSA Schedule
Integent is GSA Schedule Contract holder. A GSA schedule helps simplify selling our services to government customers.
Read More Here
News
Stay informed on Integent’s latest company updates and other important industry information. Our passion is customer success.
Read The Latest News
Videos
Learning new software doesn’t have to be difficult with our library of dozens of free training videos. Our video training always has something new.
Browse Our Training Video Library
Blog
Our industry experts share best practices and common pitfalls to avoid, in order to get the most out of your technology solutions.
Discover More

February 13, 2021

How to Use Master Projects and Subprojects with Microsoft Project Online

A Well-Built Project Schedule

Before we get into the specifics of using master projects and sub projects, lets spend a few minutes talking about the project schedule. There are many aspects to a schedule. And you may find each project manager has his or her own opinion of what makes up a well-built schedule. Although there are many different opinions of what a well-built schedule is, it's most important that the schedule is realistic and executable. The way in which a schedule is created should always require some type of structured approach. Although proper schedule development is not the topic of this post, lets talk about the work breakdown structure (WBS) and it's benefits to the project team. The Work Breakdown Structure The most important aspect of a project schedule is the WBS. Without a WBS the project schedule is destined for failure. The work to be accomplished will be unorganized and riddled with gaps. This is why it is very important to develop a proper WBS. After all, a WBS of the overall project schedule. A proper WBS will lend itself well to accurately determining resource allocation.

Developing the WBS

Defined, the WBS is a hierarchical list of all the work in a project plan. The work of the project will create deliverables when it is executed. The Microsoft project online desktop client and Power BI provide the scheduling and reporting tools necessary to communicate status of the WBS to stakeholders.  The cloud based Project Web App provides the mechanism the entire project team will utilize to successfully collaborate on and execute the project. A typical approach to develop the WBS is to start at the highest levels of the project. For instance, if working on a product development project the highest levels would consists of an organizations phased approach to product development. Once the highest level phases are in place the process of breaking down the work may commence. This process is typically referred to as decomposition. Each project manager will have a different requirement for the level of detail. Many times the detail is driven by reporting requirements from stakeholders.

Managing Complex Projects

It's no secret that projects can get out of hand quickly. What was once a small project has turned into a complex endeavor. Thousands of tasks, dozens of team members and several project managers. Sometimes these large, complex projects are better divided into smaller projects in order to have more control over them. By linking them together in a single project file you can show how they fit in a master project.

Master Projects and Subprojects

In short, a master project file is simply a collection of related projects. The projects that are inserted into the master project are referred to as subprojects or subproject files.  To link projects (subproject files) is to create intra-project dependencies.  In terms of Microsoft Project, when you insert a subproject into a master project, a MS Project icon will appear in the indicators column. Clearly indicating this is a subproject.
  • Subprojects appear as summary tasks in a master project
  • Upon clicking the summary task of a subproject all the tasks will appear upon expanding the project.
  • Typically each subproject will represent a different phase or functional group of the master project
  • If the need is to simply combine projects for reporting purposes, a temporary master project may be used.
Creating a master project allows smaller chunks of work to be delegated the appropriate teams. This helps project managers gain access and control over theirt parts of the schedule without the need to share a single project file.

Why Use Master Projects?

Most often if a Project is very large and complex using subprojects may help simplify management. Projects that contain hundreds of tasks are easier to manager when broken into subprojects and linked via intra-project dependencies. Project work containing more detail may be best broken into a smaller project. The separate project files will act as one when task dependencies are created between the subprojects using Microsoft Project Professional. A single project task from each project will be part of the dependencies and constraints created in the project management software. The types of dependencies are really not important. Just that the schedules are linked, formulating predecessor tasks and successor tasks. Each project manager will executed the tasks of the project in order to complete the project. Remember: dependencies in project management are the cornerstone of building the project timeline and critical path. And with the assistance of Project Web App, the team will have the visibility necessary into their own work. Another reason to use Master Projects and subprojects is when multiple people need access to modify the project file. Most often a project is owned and managed by a single project manager. If, however, a project is part of a large program a subproject will allow team members to focus on their work better . Below are the steps required for using master projects and subprojects with Microsoft Project Online

Creating a Master Project Schedule

  1. Open or create a new project schedule in Microsoft Project. This project can have tasks or be blank.In the Project tab, click on Subproject
  2. In the Project tab, click on Subproject

    click on the subproject button on the Project tab in Microsoft Project

  3. Find the location where you have the Subproject saved.
  4. Click Insert

    * The subproject will appear as a summary tasks with tasks collapsed and the project name in bold. * An indicator will appear in the indicators column, noting this is a subproject. a project icon indicator appears in the indicators column of the table in Microsoft Project noting this is a subproject

  5. Save the Master Project
  6. When prompted, choose whether or not to save the changes made to the subprojects. The changes made will reflect in the subproject’s individual files, too.

Inserting a Subproject in Read Only format

  1. Open or create a new project schedule. This project may be blank or have tasks.
  2. In the Project tab, click on Subproject
click on the subproject button in the MS Project ribbon
3. Find the location where you have the Subproject saved. 4. Click the Insert drop down arrow then click "Insert Read Only"
Navigate to the project file you wish to insert into the master project file
*The subproject will appear with tasks collapsed and the Project Name bolded and represented as a Summary Task. *An indicator will appear to let you know this is a subproject in read only mode.
The subproject appears in the table with an MS Project icon in the indicators column
5. Save the Master Project

Project Center Views

In the Project ribbon, confirm the Subprojects checkbox has been selected to allow the subprojects to be viewed in the table.
select the subprojects checkbox on the ms project ribbon

Checking Out Master Projects and Subprojects

If the subprojects have been inserted with read/write capabilities, you may need to expand all the subproject tasks for Project Online to recognize these have been checked out for making changes. 1. Expand all tasks by selecting the View ribbon, then Outline, then All subtasks.
From the View menu in MS Project, select to show all outlines