Create a blank project

Insert the two projects that should be related

image

 

 

View of projects I inserted.

 

image

 

Select the two tasks required to be dependent, and click the create link button

 

image

 

 

Now you can see I red bolded the text.  Also note the predecessor/successors.

image

 

Select File –> Close.  The first item saved will be your master project.

image

 

I simply named my Master Project so it’s ovbious

image

 

Subsequent saves will be for the sub-projects.  I simply selected Yes to All to save the task links I created.

image

 

Now I opened up just the Training Plan B project.  Although you see the inter-dependency, you do not see bold text. 

image

 

I then opened the master project, and here you can see the links as well as the Red Bold font was saved.

image