We have a great custom tool that allows you to change multiple Project Start Dates – so if you are interested in that … Contact Us.

However this question was around Changing Task Start Dates.
In Project, select all the Start Dates that you want to make the same date

image

Then Right-Click and choose Information…  and select the start date and choose OK.

image

You will see that the Start Dates change.

image

Enjoy.