not add domain!
Assigning Budget Resources in Microsoft Project 2010 - Integent
Call Us Today! 1.800.895.3254
sales@integent.com
Consulting & Advisory
Consulting / Advisory helps business and IT leaders make better decisions and turn strategy into execution-ready initiatives. Most engagements start with a Discovery Initiative to confirm outcomes, and build a roadmap.

Learn About Consulting
Data & AI
Data & AI delivers modern data platforms, analytics, and practical AI solutions—from assistants to agents—built on enterprise cloud tools. Integent helps you govern, deploy, and drive adoption so solutions stick and scale across your organization.
Learn About Data & AI
Support
Support keeps your solution stable, secure, and aligned with day-to-day operations. We combine functional and technical expertise with proactive monitoring, preventive maintenance, and 24/7 coverage for critical incidents.

Learn About Support
Microsoft Planner Premium
Leverage proven knowledge and experience to design and deploy Microsoft Planner Premium so your organization can manage projects, work, and resources more effectively across teams.
Learn More About Planner Premium
OnePlan
Integent can help you ensure continuity beyond Project Online by deploying OnePlan in the Microsoft Cloud—connecting portfolio governance, resources, and delivery execution for results.
Learn More About OnePlan
Microsoft Dynamics 365
Ensure business continuity with a custom cloud solution that connects your sales, service, finance, and operations teams to deliver measurable, predictable results.

Learn More About Dynamics 365
Microsoft Power Platform
Consisting of Power BI, Power Apps, Power Automate and Copilot Studio, the Microsoft Power Platform helps streamline and improve business functions.

Learn More About Power Platform
About Integent
Integent was founded in 2009 on the principles of building long-lasting relationships with customers, exceeding expectations, and providing outstanding customer service. 

We’re dedicated to providing a customized solution backed by our knowledgeable team of Microsoft experts.
Discover What Makes Us Different
News
Stay informed on Integent’s latest company updates and other important industry information. Our passion is customer success.
Read The Latest News
Videos
Learning new software doesn’t have to be difficult with our library of dozens of free training videos. Our video training always has something new.
Browse Our Training Video Library
Blog
Our industry experts share best practices and common pitfalls to avoid, in order to get the most out of your technology solutions.
Discover More

February 13, 2012

Assigning Budget Resources in Microsoft Project 2010

Budget resources. They are a great feature of Microsoft Project 2007 and Microsoft Project 2010 if only you can figure out how to use them. I had a hard time figuring it out and am thinking maybe some of you are, too. So here are the directions that will help you create and assign budget resources to your schedules so you can make both cost and work budgets visible.

First, you have to create the budget resources which can be a little tricky if you don’t know about the budget resource field.

1. Navigate to your Resource Sheet view (this can be done in the Enterprise Global for those of you working with Project Server).

2. Enter two resources; one resource for your Budgeted Cost and one for your Budgeted Work. Notice in the screenshot below that the type field has been set to Cost for the Budget Cost resource and Work for the Budget Work resource.

clip_image001

3. Insert the Budget field and set the value to Yes for both of the resources you created.

clip_image002

Now that you’ve created the resources, it’s time to figure out how to get them assigned. The first thing you need to know is that you can only assign them to the Project Summary task. This is the very first task listed and has an ID of 0. If you don’t have the Project Summary task in your schedule, do the following:

4. Navigate to the Gantt Chart and select the Format ribbon. All the way to the right, check the box next to Project Summary Task.

clip_image004

5. Assign both resources to the Project Summary task.

6. Navigate to the Task Usage view (Resource Usage would also work) and insert the columns Budget Work and Budget Cost.

7. Enter your budget cost next to the budget cost resource in the Budget Cost column.

8. Enter your budget work next to the budget work resource in the Budget Work column.

clip_image005

Congratulations! Your budget is now visible in your schedule!

Learn more tips and tricks like these in our Scheduling for Success course. You can also view a full list of our courses to find one that is right for you. If your question hasn’t been answered here, feel free to Ask the Expert a question and we’ll respond with another post soon.

Happy Scheduling!