Recently we were asked a question: In Microsoft Project 2010, can you turn on the WBS numbering to display in the task name and NOT as a separate column in the Gantt Chart? The answer is Yes.
All you need to do is check the Outline Number checkbox located on the Format tab (Gantt Chart Tools) when displaying the Gantt Chart.