not add domain!
Estimating Duration and Work in Microsoft Project - Integent
Call Us Today! 1.800.895.3254
sales@integent.com
Consulting & Advisory
Consulting / Advisory helps business and IT leaders make better decisions and turn strategy into execution-ready initiatives. Most engagements start with a Discovery Initiative to confirm outcomes, and build a roadmap.

Learn About Consulting
Data & AI
Data & AI delivers modern data platforms, analytics, and practical AI solutions—from assistants to agents—built on enterprise cloud tools. Integent helps you govern, deploy, and drive adoption so solutions stick and scale across your organization.
Learn About Data & AI
Support
Support keeps your solution stable, secure, and aligned with day-to-day operations. We combine functional and technical expertise with proactive monitoring, preventive maintenance, and 24/7 coverage for critical incidents.

Learn About Support
Microsoft Planner Premium
Leverage proven knowledge and experience to design and deploy Microsoft Planner Premium so your organization can manage projects, work, and resources more effectively across teams.
Learn More About Planner Premium
OnePlan
Integent can help you ensure continuity beyond Project Online by deploying OnePlan in the Microsoft Cloud—connecting portfolio governance, resources, and delivery execution for results.
Learn More About OnePlan
Microsoft Dynamics 365
Ensure business continuity with a custom cloud solution that connects your sales, service, finance, and operations teams to deliver measurable, predictable results.

Learn More About Dynamics 365
Microsoft Power Platform
Consisting of Power BI, Power Apps, Power Automate and Copilot Studio, the Microsoft Power Platform helps streamline and improve business functions.

Learn More About Power Platform
About Integent
Integent was founded in 2009 on the principles of building long-lasting relationships with customers, exceeding expectations, and providing outstanding customer service. 

We’re dedicated to providing a customized solution backed by our knowledgeable team of Microsoft experts.
Discover What Makes Us Different
News
Stay informed on Integent’s latest company updates and other important industry information. Our passion is customer success.
Read The Latest News
Videos
Learning new software doesn’t have to be difficult with our library of dozens of free training videos. Our video training always has something new.
Browse Our Training Video Library
Blog
Our industry experts share best practices and common pitfalls to avoid, in order to get the most out of your technology solutions.
Discover More

July 9, 2013

Estimating Duration and Work in Microsoft Project

We recently received a question from a user regarding Work and Duration estimates. She wanted to know how to estimate both and let MS Project calculate the percentage of a person’s time that would be allocated to the task. In a nutshell, here’s how to accomplish this:

If you are entering estimates BEFORE you assign resources, follow the steps below:

  1. Set your task type for all existing tasks and all new tasks to ‘Fixed Work’
  2. Enter both the duration and work estimates for each task
  3. Assign your resources

If you are making changes to an estimate AFTER resources are assigned, you need change the task type accordingly. The scheduling formula is Duration x Units = Work. If you change one of those variables, then project has to recalculate one of the other variables. So, if resources are already assigned and you need to change the DURATION estimate, follow the steps below:

  1. Make sure the task type is set to Fixed Work
  2. Change your Duration and the Work should remain the same, the units for the resource will change although you won’t see it appear on the Gantt Chart (to see the current assignment units go to the Resource Usage View and insert the column ‘Peak’)

If resources are assigned and you want to change the WORK estimate, follow the steps below:

  1. Make sure the task type is set to Fixed Duration
  2. Change your work estimate and the Duration should remain the same, the Units for the resource will change although you won’t see it appear on the Gantt Chart (to see the current assignment units go to the Resource Usage View and insert the column ‘Peak’)

Just in case you aren’t familiar with task types and how to change them….

For existing tasks:

  1. Highlight all tasks you want to change
  2. Go to the Task Ribbon
  3. Click on the Information button
  4. Select the Advanced Tab and change your task type

To set the task type for all new tasks:

  1. File --> Options --> Schedule tab
  2. You will see the option to change your task type for all new tasks

Learn more tips and tricks like this one by attending one of our webinars or training courses!

Happy Scheduling! Open-mouthed smile