not add domain!
Preventing Resource Over Allocation in Microsoft Project Server - Integent
Call Us Today! 1.800.895.3254
sales@integent.com
Consulting & Advisory
Consulting / Advisory helps business and IT leaders make better decisions and turn strategy into execution-ready initiatives. Most engagements start with a Discovery Initiative to confirm outcomes, and build a roadmap.

Learn About Consulting
Data & AI
Data & AI delivers modern data platforms, analytics, and practical AI solutions—from assistants to agents—built on enterprise cloud tools. Integent helps you govern, deploy, and drive adoption so solutions stick and scale across your organization.
Learn About Data & AI
Support
Support keeps your solution stable, secure, and aligned with day-to-day operations. We combine functional and technical expertise with proactive monitoring, preventive maintenance, and 24/7 coverage for critical incidents.

Learn About Support
Microsoft Planner Premium
Leverage proven knowledge and experience to design and deploy Microsoft Planner Premium so your organization can manage projects, work, and resources more effectively across teams.
Learn More About Planner Premium
OnePlan
Integent can help you ensure continuity beyond Project Online by deploying OnePlan in the Microsoft Cloud—connecting portfolio governance, resources, and delivery execution for results.
Learn More About OnePlan
Microsoft Dynamics 365
Ensure business continuity with a custom cloud solution that connects your sales, service, finance, and operations teams to deliver measurable, predictable results.

Learn More About Dynamics 365
Microsoft Power Platform
Consisting of Power BI, Power Apps, Power Automate and Copilot Studio, the Microsoft Power Platform helps streamline and improve business functions.

Learn More About Power Platform
About Integent
Integent was founded in 2009 on the principles of building long-lasting relationships with customers, exceeding expectations, and providing outstanding customer service. 

We’re dedicated to providing a customized solution backed by our knowledgeable team of Microsoft experts.
Discover What Makes Us Different
News
Stay informed on Integent’s latest company updates and other important industry information. Our passion is customer success.
Read The Latest News
Videos
Learning new software doesn’t have to be difficult with our library of dozens of free training videos. Our video training always has something new.
Browse Our Training Video Library
Blog
Our industry experts share best practices and common pitfalls to avoid, in order to get the most out of your technology solutions.
Discover More

July 13, 2013

Preventing Resource Over Allocation in Microsoft Project Server

This is part 2 in a 4 part series on Managing Resource Allocation in Project Server. If you missed part 1, check it out here before you read this post.

Here are a few tips on preventing over allocations:

Assign Generic Resources first. If you do this, you can easily determine exactly how many hours of availability is needed over a set duration. Follow along…

First, you need to make sure you have NOT loaded resource summary assignments. (more information can be found in part 1 of this series) Once you’ve done this, follow the steps below:

  1. Apply the Resource Usage View
  2. Insert the Work, Start and Finish columns
  3. Find the generic resource you want to replace with a named resource and note the total number of Work hours and the start and finish date for this resource’s assignments

clip_image001

In the example above, I can see that I need a PM to do 32 hours of work between 7/3 and 7/8.

Next, you want to use the filters in the Team Builder to find an available resource:

  1. On the Resource Ribbon, Select Add Resources and then Build Team from Enterprise
  2. Use the availability filter to look for resources who are available to do 32 hours of work from 7/3 to 7/8
  3. clip_image002
  4. Click Apply and the list of team members will be filtered based on their availability
  5. Select the resource on the left and select Project Manager on the right
  6. Click Replace and then click OK

I know what some of you are thinking right now. “My situation is NOT that simple!” Perhaps you need multiple resources to replace one Generic Resource. Or perhaps you don’t use Generic Resources at all. That’s okay. There is still another feature that can help you prevent over allocations.

After you have entered your estimates (for this to work, you would have to have entered duration estimates at the least) and are ready to assign resources, follow the steps below:

  1. Make sure you have Loaded Resource Summary assignments (more information can be found in part 1 of this series)
  2. Go to the Resource Tab and select Assign Resources.
  3. In the Assign Resources dialog box, expand the Resource List Options
  4. clip_image003
  5. Select the task you want to assign a resource to
  6. Check the box next to Available to work
  7. Enter the estimated number of hours the resource will work over the course of the duration you estimate

clip_image004

This list of resources will be filtered to display only those who have the availability you entered above AND here’s the best part: It is filtering based on ALL the resource’s assignments across the Enterprise!

I have one final tip for you. When the little red man appears in the indicator column clip_image006 , DO SOMETHING ABOUT IT