Call Us Today! 1-800-895-3254
[email protected]
Microsoft Training
Integent offers a comprehensive portfolio of training services, with an ideal fit for every organization. Ranging from general courses to custom solutions, we have you covered.
Learn About TrainingSee Full list of Courses
Microsoft Consulting
Integent provides consulting services for a variety of Microsoft applications including Microsoft Project, Project Online, Project for the Web, Dynamics 365, and Microsoft SharePoint.
Learn About Consulting
Microsoft Support
Microsoft technologies set the standard for project portfolio management, business applications, collaboration, and more. Integent has flexible solutions to support every customer.
Learn About Support
Microsoft Project
Integent has the knowledge and experience to help design and deploy a solution to help your organization manage projects and resources more effectively
Learn More About Microsoft Project
Microsoft Dynamics 365
Integent can help you nsure business continuity with a custom cloud solution that connects sales, service, finance, and operations teams to deliver results.
Learn More About Dynamics 365
Microsoft SharePoint
SharePoint is Microsoft’s collaboration platform that is a place where team members can communicate, exchange data, share files and much more.
Learn More About Microsoft SharePoint
Microsoft Power Platform
Consisting of Power BI, Power Apps, Power Automate and Power Virtual Agents, the Microsoft Power Platform helps streamline and improve business functions.
Learn More About The Power Platform
About Integent
Integent was founded in 2009 on the principles of building long-lasting relationships with customers, exceeding expectations, and providing outstanding customer service. 

We’re dedicated to providing a customized solution backed by our knowledgeable team of Microsoft experts.
Discover What Makes Us Different
GSA Schedule
Integent is GSA Schedule Contract holder. A GSA schedule helps simplify selling our services to government customers.
Read More Here
News
Stay informed on Integent’s latest company updates and other important industry information. Our passion is customer success.
Read The Latest News
Videos
Learning new software doesn’t have to be difficult with our library of dozens of free training videos. Our video training always has something new.
Browse Our Training Video Library
Blog
Our industry experts share best practices and common pitfalls to avoid, in order to get the most out of your technology solutions.
Discover More

February 13, 2012

Assigning Budget Resources in Microsoft Project 2010

Budget resources. They are a great feature of Microsoft Project 2007 and Microsoft Project 2010 if only you can figure out how to use them. I had a hard time figuring it out and am thinking maybe some of you are, too. So here are the directions that will help you create and assign budget resources to your schedules so you can make both cost and work budgets visible.

First, you have to create the budget resources which can be a little tricky if you don’t know about the budget resource field.

1. Navigate to your Resource Sheet view (this can be done in the Enterprise Global for those of you working with Project Server).

2. Enter two resources; one resource for your Budgeted Cost and one for your Budgeted Work. Notice in the screenshot below that the type field has been set to Cost for the Budget Cost resource and Work for the Budget Work resource.

clip_image001

3. Insert the Budget field and set the value to Yes for both of the resources you created.

clip_image002

Now that you’ve created the resources, it’s time to figure out how to get them assigned. The first thing you need to know is that you can only assign them to the Project Summary task. This is the very first task listed and has an ID of 0. If you don’t have the Project Summary task in your schedule, do the following:

4. Navigate to the Gantt Chart and select the Format ribbon. All the way to the right, check the box next to Project Summary Task.

clip_image004

5. Assign both resources to the Project Summary task.

6. Navigate to the Task Usage view (Resource Usage would also work) and insert the columns Budget Work and Budget Cost.

7. Enter your budget cost next to the budget cost resource in the Budget Cost column.

8. Enter your budget work next to the budget work resource in the Budget Work column.

clip_image005

Congratulations! Your budget is now visible in your schedule!

Learn more tips and tricks like these in our Scheduling for Success course. You can also view a full list of our courses to find one that is right for you. If your question hasn’t been answered here, feel free to Ask the Expert a question and we’ll respond with another post soon.

Happy Scheduling!

© Copyright 2023 | Integent.com | All Rights Reserved
linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram