As previously discussed Project uses different types of calendars for different purposes. In this topic we will focus on resource calendars. A resource calendar controls the times in which a resource is available to work, better known as working and nonworking time. Project uses teh resource calendar to determine when work for a resource can be scheduled. Resource calendars only apply to work resources, that is people and equipment, not to material or cost resources.