Introduction
This blog details how to move the WSS workspace between sub-sites. This may occur if a project is moved between programmes
Process Overview
By default, Microsoft Office Project Professional 2007 creates a project workspace site on Windows SharePoint Services 3.0 when it publishes a project. When a sub-project creates a workspace, the user has the option of also creating the project workspace as a sub-site of the programme. This creates a hierarchy of sites as shown in Figure 1, where Programme1 has two sub projects (A & B), and Programme2 has two sub projects (C & D).
Figure 1 - Programme and PRoject Workspace relationships
If Project C is moved between programmes (due to reorganisation or setup issues) then the WSS site by default not moved. The following steps show how to move the WSS site. The example will show Project C moving to be part of Programme1 (Figure 2).