Call Us Today! 1-800-895-3254
[email protected]
Microsoft Training
Integent offers a comprehensive portfolio of training services, with an ideal fit for every organization. Ranging from general courses to custom solutions, we have you covered.
Learn About TrainingSee Full list of Courses
Microsoft Consulting
Integent provides consulting services for a variety of Microsoft applications including Microsoft Project, Project Online, Project for the Web, Dynamics 365, and Microsoft SharePoint.
Learn About Consulting
Microsoft Support
Microsoft technologies set the standard for project portfolio management, business applications, collaboration, and more. Integent has flexible solutions to support every customer.
Learn About Support
Microsoft Project
Integent has the knowledge and experience to help design and deploy a solution to help your organization manage projects and resources more effectively
Learn More About Microsoft Project
Microsoft Dynamics 365
Integent can help you nsure business continuity with a custom cloud solution that connects sales, service, finance, and operations teams to deliver results.
Learn More About Dynamics 365
Microsoft SharePoint
SharePoint is Microsoft’s collaboration platform that is a place where team members can communicate, exchange data, share files and much more.
Learn More About Microsoft SharePoint
Microsoft Power Platform
Consisting of Power BI, Power Apps, Power Automate and Power Virtual Agents, the Microsoft Power Platform helps streamline and improve business functions.
Learn More About The Power Platform
About Integent
Integent was founded in 2009 on the principles of building long-lasting relationships with customers, exceeding expectations, and providing outstanding customer service. 

We’re dedicated to providing a customized solution backed by our knowledgeable team of Microsoft experts.
Discover What Makes Us Different
GSA Schedule
Integent is GSA Schedule Contract holder. A GSA schedule helps simplify selling our services to government customers.
Read More Here
News
Stay informed on Integent’s latest company updates and other important industry information. Our passion is customer success.
Read The Latest News
Videos
Learning new software doesn’t have to be difficult with our library of dozens of free training videos. Our video training always has something new.
Browse Our Training Video Library
Blog
Our industry experts share best practices and common pitfalls to avoid, in order to get the most out of your technology solutions.
Discover More

July 9, 2013

Estimating Duration and Work in Microsoft Project

We recently received a question from a user regarding Work and Duration estimates. She wanted to know how to estimate both and let MS Project calculate the percentage of a person’s time that would be allocated to the task. In a nutshell, here’s how to accomplish this:

If you are entering estimates BEFORE you assign resources, follow the steps below:

  1. Set your task type for all existing tasks and all new tasks to ‘Fixed Work’
  2. Enter both the duration and work estimates for each task
  3. Assign your resources

If you are making changes to an estimate AFTER resources are assigned, you need change the task type accordingly. The scheduling formula is Duration x Units = Work. If you change one of those variables, then project has to recalculate one of the other variables. So, if resources are already assigned and you need to change the DURATION estimate, follow the steps below:

  1. Make sure the task type is set to Fixed Work
  2. Change your Duration and the Work should remain the same, the units for the resource will change although you won’t see it appear on the Gantt Chart (to see the current assignment units go to the Resource Usage View and insert the column ‘Peak’)

If resources are assigned and you want to change the WORK estimate, follow the steps below:

  1. Make sure the task type is set to Fixed Duration
  2. Change your work estimate and the Duration should remain the same, the Units for the resource will change although you won’t see it appear on the Gantt Chart (to see the current assignment units go to the Resource Usage View and insert the column ‘Peak’)

Just in case you aren’t familiar with task types and how to change them….

For existing tasks:

  1. Highlight all tasks you want to change
  2. Go to the Task Ribbon
  3. Click on the Information button
  4. Select the Advanced Tab and change your task type

To set the task type for all new tasks:

  1. File --> Options --> Schedule tab
  2. You will see the option to change your task type for all new tasks

Learn more tips and tricks like this one by attending one of our webinars or training courses!

Happy Scheduling! Open-mouthed smile